I have five operators and three processors. Operators are connected to a dispatcher. They move boxes from a queue to the processor and process the operation. When I run my model the dashboard shows waiting for transporter is 50% but I am struggling to understand how this is possible. (My model is too large to upload)

FlexSim 23.0.7
taskexecutorsoperater
5 |100000

Up to 12 attachments (including images) can be used with a maximum of 23.8 MiB each and 47.7 MiB total.

1 Answer

Jason Lightfoot avatar image
0 Likes"
Jason Lightfoot answered mohammadmajd commented

Use a state gantt for the processors and track the operation as it runs. Verify the states are being set correctly. If the operators go off shift are the processors still waiting for transport?