DaniCor asked Jeanette F commented

Replenishment Depending Queue


Hi mates!

I am struggling with the replenishment of flow items accordding the level of my QUEUE, for example if the level in the QUEUE is less than 9000 considering actual stock plus the stock in transit I need to create a new purchase requition if I create today the requisition the purchase will arrive in 120 days average with standard deviation of 20 days according de historical data, just in case at the beginning of the run I start with a stock of 9800 flowitems. I look forward to you response!

captura-de-pantalla-2023-12-12-230703.png


FlexSim 23.2.2
stockmaterial replenishmentsupplier model
· 4
5 |100000

Up to 12 attachments (including images) can be used with a maximum of 23.8 MiB each and 47.7 MiB total.

DaniCor avatar image DaniCor commented ·
I need to add that the replenishment quantity must be 5600 or more according the minimum order quantity, or the quantity needed for the next 120 days wich is the leat time of a new purchase requistion. Best regards!
0 Likes 0 ·
Jason Lightfoot avatar image Jason Lightfoot ♦ DaniCor commented ·
Be careful - this looks like a duplicate of this question - duplicates contravene our site rules.
0 Likes 0 ·
DaniCor avatar image DaniCor Jason Lightfoot ♦ commented ·
This question is different, in this case is for a policy of continuous review
0 Likes 0 ·
Jeanette F avatar image Jeanette F ♦♦ commented ·

Hi @DaniCor, was Julio R's answer helpful? If so, please click the "Accept" button at the bottom of their answer. Or if you still have questions, add a comment and we'll continue the conversation.

If we haven't heard back from you within 3 business days we'll auto-accept an answer, but you can always comment back to reopen your question.

0 Likes 0 ·

1 Answer

·
Julio R avatar image
0 Likes"
Julio R answered Jason Lightfoot commented

Hello @DaniCor ,

There are many ways to do this, can you share your model so we can see how have are you atempting to do it?

· 2
5 |100000

Up to 12 attachments (including images) can be used with a maximum of 23.8 MiB each and 47.7 MiB total.

DaniCor avatar image DaniCor commented ·

Hi mate

I was using an Inter-arrival time per Batch processing where each 122 days in average resource 5600 flowitems but not consider the stock level on the queue if there is less than 9000 to make a replenishment

SIMULACION PROPUESTA CON DISPATCHER.fsm

I saw that can be possible with a dispatcher but only works programming in queue not in source until I tried

0 Likes 0 ·
Jason Lightfoot avatar image Jason Lightfoot ♦ DaniCor commented ·
Detect an event to trigger the ordering based on the number of subnodes in the queue. Use that event (eg. in a process flow) to then create the items after a delay representing the transport time.
1 Like 1 ·