question

Jonathan_Huang avatar image
0 Likes"
Jonathan_Huang asked Jonathan_Huang commented

Operator Task

Hi everyone


I have one question


1712908473021.png


Processor 1, 2 both use operator for processing

Operator 1 after completed processing in Processor 2 will wait in Processor 2. He only come back to Processor 1 right after next flow item come into Processor 1.

How to make him come back to Processor 1 right after finished processing in Processor 2 without using Process flow?


Thánks and best regards


FlexSim 23.1.2
operator task
1712908473021.png (215.3 KiB)
5 |100000

Up to 12 attachments (including images) can be used with a maximum of 23.8 MiB each and 47.7 MiB total.

1 Answer

Felix Möhlmann avatar image
1 Like"
Felix Möhlmann answered Jonathan_Huang commented

You can tell the operator to move to a specific location if there are no other pending tasks in its On Resource Available trigger.

1712913192061.png


1712913192061.png (5.5 KiB)
· 1
5 |100000

Up to 12 attachments (including images) can be used with a maximum of 23.8 MiB each and 47.7 MiB total.

Jonathan_Huang avatar image Jonathan_Huang commented ·
Thank you Mr Felix
0 Likes 0 ·