question

Abdelrahman Mohamed avatar image
0 Likes"
Abdelrahman Mohamed asked Abdelrahman Mohamed commented

Maintenance and Preparation

I need to have a maintenance for 3 machines for 8 hours each 30 days and a preparation for one machine every 8 hours for 1.75 hours and the operator must do this


FlexSim 24.1.0
maintenancepreparation time
5 |100000

Up to 12 attachments (including images) can be used with a maximum of 23.8 MiB each and 47.7 MiB total.

1 Answer

·
Felix Möhlmann avatar image
0 Likes"
Felix Möhlmann answered Abdelrahman Mohamed commented

You can use time tables or the MTBF/MTTR to manage these events. (Just because it has "failure" and "repair" in the name doesn't mean that the down time of the MTBF/MTTR can't be used in other capacities like maintenance or setup as well)

https://docs.flexsim.com/en/24.0/Reference/Tools/TimeTables/TimeTables.html

https://docs.flexsim.com/en/24.0/Reference/Tools/MtbfMttr/MtbfMttr.html

· 5
5 |100000

Up to 12 attachments (including images) can be used with a maximum of 23.8 MiB each and 47.7 MiB total.

Abdelrahman Mohamed avatar image Abdelrahman Mohamed commented ·
I just tried both but i have problem with MTBF/MTTR that the model did not repeat the breakdown so how should i do this?
0 Likes 0 ·
Felix Möhlmann avatar image Felix Möhlmann Abdelrahman Mohamed commented ·
Can you post your model, or at least the settings of the MTBF?
0 Likes 0 ·
Abdelrahman Mohamed avatar image Abdelrahman Mohamed Felix Möhlmann commented ·

pt3.fsm
i just do it on time table but i need an operator to do it for me and cant do it on mtbfmttr

0 Likes 0 ·
pt3.fsm (57.2 KiB)
Show more comments

Write an Answer

Hint: Notify or tag a user in this post by typing @username.

Up to 12 attachments (including images) can be used with a maximum of 23.8 MiB each and 47.7 MiB total.