Hello.
The process flow of the attached model moves only one operator. If you group by adding Operator, it will not proceed. I want to add several people to make a model that analyzes the right number of people, please help!
Thank you!
Hello.
The process flow of the attached model moves only one operator. If you group by adding Operator, it will not proceed. I want to add several people to make a model that analyzes the right number of people, please help!
Thank you!
The zone in the subflow that only allows a single token to enter prevents more than one operator from working at a time. Instead of using that zone you can check the option "Run Tokens one at a time" in the Run Sub Flow activity. But then you have to make sure that the pulled items are assigned to a different label than the pulled 'pick tokens'. Otherwise you run into issues where the "pulled" label is overwritten too soon.
Another issue is that due to how the timing works out, the operators might load the same pallet which means some operators end up without a pallet which leads to errors when items are supposed to be moved to the pallet. You can either use a zone here so tokens load pallets one at a time or pull the pallets from a list to prevent two tokens getting the same reference.
Thank you so much for your detailed explanation and response.
Thank you again
14 People are following this question.
FlexSim can help you understand and improve any system or process. Transform your existing data into accurate predictions.
FlexSim is a fully 3D simulation software environment. FlexSim can be used to simulate any process in any industry.
FlexSim®, FlexSim Healthcare™, Problem Solved.®, the FlexSim logo, the FlexSim X-mark, and the FlexSim Healthcare logo with stylized Caduceus mark are trademarks of FlexSim Software Products, Inc. All rights reserved.
Privacy | Do not sell or share my personal information | Cookie preferences | Report noncompliance | Terms of use | Legal | © Autodesk Inc. All rights reserved