Hello team,
Box should move to other station when it is available.
Boxes should not accumulate between the stations
One box process on combiner and then transfer to other station if the station is available.
Thanks in advance
Hello team,
Box should move to other station when it is available.
Boxes should not accumulate between the stations
One box process on combiner and then transfer to other station if the station is available.
Thanks in advance
For the flow on the conveyors, use the Area Restriction options in the stations's triggers. To control the entry onto the conveyors, you can close the combiner's output after each exit and have it open again once the item resumes from the first station.
Thanks @Felix Möhlmann
If there is a station in between rework linked stations the logic is not working.
So either move that station back or decide on the rework on the previous station (Set Label option from OnProcessFinish trigger)
12 People are following this question.
FlexSim can help you understand and improve any system or process. Transform your existing data into accurate predictions.
FlexSim is a fully 3D simulation software environment. FlexSim can be used to simulate any process in any industry.
FlexSim®, FlexSim Healthcare™, Problem Solved.®, the FlexSim logo, the FlexSim X-mark, and the FlexSim Healthcare logo with stylized Caduceus mark are trademarks of FlexSim Software Products, Inc. All rights reserved.
Privacy | Do not sell or share my personal information | Cookie preferences | Report noncompliance | Terms of use | Legal | © 2025 Autodesk Inc. All rights reserved