I’m not sure I understand the ActivityStartTime, the ActivityFinishTime and the ActivityProcessTime: Shouldn’t the finish time minus the start time equal the process time?
I’m not sure I understand the ActivityStartTime, the ActivityFinishTime and the ActivityProcessTime: Shouldn’t the finish time minus the start time equal the process time?
The processing time doesn't necessarily start when the activity starts. For example, if the activity requires staff or a location then the processing time doesn't start until all the resources have been acquired and either arrive at the patient or the patient arrives at them.
3 People are following this question.
FlexSim can help you understand and improve any system or process. Transform your existing data into accurate predictions.
FlexSim is a fully 3D simulation software environment. FlexSim can be used to simulate any process in any industry.
FlexSim®, FlexSim Healthcare™, Problem Solved.®, the FlexSim logo, the FlexSim X-mark, and the FlexSim Healthcare logo with stylized Caduceus mark are trademarks of FlexSim Software Products, Inc. All rights reserved.
Privacy | Do not sell or share my personal information | Cookie preferences | Report noncompliance | Terms of use | Legal | © Autodesk Inc. All rights reserved