process flow item creation by about five hundred objects like processors

A model has a very big item table of 500 item rows to be created in the source.

Yes item has its own item type number.

Each item has its own cycle time and each is same or different.

And the items should be created when all items move along each different route and enter to 500 processors.

How can I make the process flow model of it?

500 processors can be grouped to 80 groups.

I found the event trigger creation to be used but it receive the trigger from one object.

How can I solve it?

I need help.

FlexSim 17.0.3
item objects
5 |100000

Up to 12 attachments (including images) can be used with a maximum of 23.8 MiB each and 47.7 MiB total.

1 Answer

Jeff Nordgren avatar image
0 Likes"
Jeff Nordgren answered David Seo commented

@david.seo,

Will the answer to your question here help in answering this question?

· 2
5 |100000

Up to 12 attachments (including images) can be used with a maximum of 23.8 MiB each and 47.7 MiB total.

David Seo avatar image David Seo commented ·

Yes. Thank you @Jeff Nordgre

I found to get my the way to solve it by your guide.

0 Likes 0 ·
David Seo avatar image David Seo commented ·

@Jeff Nordgren Thank you very much.

This issue was solved but the flow items created in the queue_in replacing with Source (the created items exist in the List of it) should be pulled from the list by down stream queues's send message trigger. And then the items should start in the model.

The detail question about it is https://answers.flexsim.com/questions/36462/when-many-queues-want-the-flow-items-to-move-from.html.

How can I do it?

0 Likes 0 ·