Hi everyone,

I'm building a production plant where i first need to divide different flowitems through a separator in accordance to a prefixed quantity set in the Source Schedule. Since i'm not really expert i'm struggling to find a solution to that.

Is there a more efficient way to do the same operation?

I'm uploading a similar model below

split.fsm

Thanks in advance

FlexSim 18.1.0
separator
split.fsm (25.0 KiB)
5 |100000

Up to 12 attachments (including images) can be used with a maximum of 23.8 MiB each and 47.7 MiB total.

1 Answer

·
David Chas avatar image
0 Likes"
David Chas answered Filippo A commented

Hi!!

Your idea is good, but you are using the Split label in the wrong way. If you use the label like the attached image the model runs correctly.

I hope this will be useful for you!


split.jpg (59.1 KiB)
12803-split.fsm (25.0 KiB)
· 1
5 |100000

Up to 12 attachments (including images) can be used with a maximum of 23.8 MiB each and 47.7 MiB total.

Filippo A avatar image Filippo A commented ·

thanks you very much David.