Make a Planning list

Hello everyone.

I have this kind of exemple in my main project and I have a trouble with making a production list.

In fact, I have only 2 sources.

I want, for exemple, 3 times Source1 flowitems and 3 times Source2 flowitems but can be variable ( ex : 1 x Source1 and 2 x Source2 / 5 x Source1 and 1 x Source2 OR 1st Source2 and after Source1)

Is it possible to make this an order and with QTY in my GlobalTable and with this Table information ?

Prepare all informations in GlobalTable ? I'll put the order in GlobalTable with qty

Thank you.


ex9.fsm

FlexSim 18.1.1
globaltableorder
11.png (168.0 KiB)
ex9.fsm (26.3 KiB)
5 |100000

Up to 12 attachments (including images) can be used with a maximum of 23.8 MiB each and 47.7 MiB total.

1 Answer

·
Joshua S avatar image
0 Likes"
Joshua S answered

You can do all of that in an "Arrival Schedule" for a single source. Here's an example model. You can increase the size of the table to accommodate how many arrivals you have. Have 2 different types arrive at the same time to simulate 2 sources. have the Type you want created first be on top of the next item created at the same time to have priority.make-a-planning-list.fsm


5 |100000

Up to 12 attachments (including images) can be used with a maximum of 23.8 MiB each and 47.7 MiB total.

Write an Answer

Hint: Notify or tag a user in this post by typing @username.

Up to 12 attachments (including images) can be used with a maximum of 23.8 MiB each and 47.7 MiB total.