question

Ahmartiago A avatar image
0 Likes"
Ahmartiago A asked Ahmartiago A commented

how to stop and resume object with some condition

Hi, I have some problem with my flexsim. i want the processor 1 and processor 2 stop input after they send 1 part and resume input if there are only 5 parts in the rack. what can i use? is send message can solve it? I really appreciate your help!

vmi.fsm

send message
vmi.fsm (27.5 KiB)
5 |100000

Up to 12 attachments (including images) can be used with a maximum of 23.8 MiB each and 47.7 MiB total.

1 Answer

·
gilbert jerald avatar image
1 Like"
gilbert jerald answered Ahmartiago A commented

@Ahmartiago A ·

Hi,

I have altered your model, now the model works as per your constraint and I have attached it for your reference have a look at it.

support-processor-message.fsm

Thanks


· 1
5 |100000

Up to 12 attachments (including images) can be used with a maximum of 23.8 MiB each and 47.7 MiB total.

Ahmartiago A avatar image Ahmartiago A commented ·

Thank You for your Answer @gilbert jerald

0 Likes 0 ·

Write an Answer

Hint: Notify or tag a user in this post by typing @username.

Up to 12 attachments (including images) can be used with a maximum of 23.8 MiB each and 47.7 MiB total.