question

Mariam R avatar image
0 Likes"
Mariam R asked Braydn T converted comment to answer

Run a model with a given schedule

My model consists of 3 lines, i have demand per shift (ton/shift) shown in the attached excel sheet, that i need to simulate, each day consists of 3 shifts, each shift is 8 hours, i want to run this model for 60 shifts (continuously), and i need to make sure that each throughput (box) is in tonnes, so if the target of the first shift for the first line is 5 ton/shift, i'll find at the racks 5 boxes.

Please let us know if you can help :)

08-03-19.fsm

3-lines.xlsx

FlexSim 18.2.3
scheduled simulation
08-03-19.fsm (39.9 KiB)
3-lines.xlsx (9.6 KiB)
· 1
5 |100000

Up to 12 attachments (including images) can be used with a maximum of 23.8 MiB each and 47.7 MiB total.

Mariam R avatar image Mariam R commented ·
0 Likes 0 ·

1 Answer

·
Joshua S avatar image
0 Likes"
Joshua S answered

Your shifts consist of non integer numbers, so how do you want 1.5 and 7.98 tonnes represented in your model on the racks?

· 2
5 |100000

Up to 12 attachments (including images) can be used with a maximum of 23.8 MiB each and 47.7 MiB total.

Mariam R avatar image Mariam R commented ·

@Joshua S, can the model run for non integer numbers? if not, the current model approximates it, my top priority for now is to run the model continuously for 60 shifts

0 Likes 0 ·
Joshua S avatar image Joshua S Mariam R commented ·

What I mean is your target is 1.5 or 7.98 tonnes, so what do you want to see in the Racks? By what you shared before, 1 box=1 tonne, so your throughput will only be whole numbers.

0 Likes 0 ·

Write an Answer

Hint: Notify or tag a user in this post by typing @username.

Up to 12 attachments (including images) can be used with a maximum of 23.8 MiB each and 47.7 MiB total.