Two operators operate the same equipment simultaneously

I need to simulate a process in which two operators operate the same equipment simultaneously. How do I configure the machine to distribute the task to two operators? Can you help me ?model-01.fsm

FlexSim 18.2.3
operatorprocessorsimulate a hardware
model-01.fsm (35.1 KiB)
5 |100000

Up to 12 attachments (including images) can be used with a maximum of 23.8 MiB each and 47.7 MiB total.

1 Answer

·
tannerp avatar image
0 Likes"
tannerp answered tannerp commented

You could select the "Use Operator(s) for Process" box and then put 2 for the "Number of Operators" as shown below.

Unless you're looking for something else. Feel free to comment back with more details about what you'd like your operators to do exactly so we can provide a more detailed answer.


· 1
5 |100000

Up to 12 attachments (including images) can be used with a maximum of 23.8 MiB each and 47.7 MiB total.

tannerp avatar image tannerp commented ·

Note that you'd also have to use a Dispatcher with 2 or more operators connected.