I have a model of a bakery production line. There are 8 operators, 4 do a 12 hour shift then the next 4 take over while the others go off shift. While on shift, each operator gets a 20 minute break, when this happens, operator X takes over.
I have it working for a the mixer on the first shift with operator X taking over but it doesn't seem to work for the process of moving a flow item from a queue to a processor?
The other issue I have is operators 5-8 don't go to the processors or 'start work'?
My model is attached, any help would be greatly appreciated. v8.fsm
Thank you