question

Felipe P2 avatar image
0 Likes"
Felipe P2 asked Braydn T answered

Why task executers cant travel empty?

stl.fsmI am working with this model and I set up the process flow so that the task executers can travel along the network being empty. I don´t know why it´s not working.

Does somebody know how to fix this?

FlexSim 19.2.3
task executeragv network
stl.fsm (48.3 KiB)
5 |100000

Up to 12 attachments (including images) can be used with a maximum of 23.8 MiB each and 47.7 MiB total.

1 Answer

·
Braydn T avatar image
0 Likes"
Braydn T answered

@Felipe P2

They can. You need to have a source in your process flow. Right now, no tokens are created, so there is not hing to acquire the resource and start the tasks. Add a scheduled or inter arrival source to the beginning of your process flow chunk.

I would also recommend going through the tutorials. This question is answered there: https://docs.flexsim.com/en/19.2/Tutorials/ProcessFlow/Tutorial1UsingSharedAssets/UsingSharedAssetsOverview/

5 |100000

Up to 12 attachments (including images) can be used with a maximum of 23.8 MiB each and 47.7 MiB total.

Write an Answer

Hint: Notify or tag a user in this post by typing @username.

Up to 12 attachments (including images) can be used with a maximum of 23.8 MiB each and 47.7 MiB total.