Dears Colaborators. How to model an MTBF / MTTR for when a processor has processed a given number of flowitems (batch)

FlexSim 20.0.0
flexsim 20.0.0
5 |100000

Up to 12 attachments (including images) can be used with a maximum of 23.8 MiB each and 47.7 MiB total.

1 Answer

Joerg Vogel avatar image
0 Likes"
Joerg Vogel answered

You stop the processor. You send a delayed message to an object that isn’t stopped. You let resume the stopped processor by this message. The delay time can be statistical distributed.

Process Flow

The same doing, but instead of a message event to delay resuming, you need only an delay activity.

Another approach: You use the setup time of a processor to initiate a repair or maintenance of the processor for the n-th item. Here you can call very simple an operator to assist the setup.