Hi Flexsim,
In my current model, there are 3 racks and 2 ASRS stagger arrangement. I want to modify ASRS that just can move items to the racks between it. How can I do?
The attachment is as follows.Thanks in advance.
Hi Flexsim,
In my current model, there are 3 racks and 2 ASRS stagger arrangement. I want to modify ASRS that just can move items to the racks between it. How can I do?
The attachment is as follows.Thanks in advance.
If I understood you correctly, you want ASRS1 to transport items to Rack 1 and 2 and ASRS2 to Rack 2 and 3?
You could have the queue push the transport task sequences to a list and add the port as a Push Argument field (this requires editing the code of the pick options as shown below).
In a small Process Flow, tokens representing the ASRS can then pull task sequences with an eligile port (<3 for ASRS1 and >1 for ASRS2)
12 People are following this question.
FlexSim can help you understand and improve any system or process. Transform your existing data into accurate predictions.
FlexSim is a fully 3D simulation software environment. FlexSim can be used to simulate any process in any industry.
FlexSim®, FlexSim Healthcare™, Problem Solved.®, the FlexSim logo, the FlexSim X-mark, and the FlexSim Healthcare logo with stylized Caduceus mark are trademarks of FlexSim Software Products, Inc. All rights reserved.
Privacy | Do not sell or share my personal information | Cookie preferences | Report noncompliance | Terms of use | Legal | © Autodesk Inc. All rights reserved