task sequence-load-unload

I have a once upstream processor connected to 2 downstream processor, two operators move the completed parts from the upstream processor to the downstream processors, and then they follow a task sequence in the downstream processors, how can I tell the upstream processor to use the task subflow-task sequence I created for each individual operator to move the items to independent stations, each operator work on his own in a separate station(processor)

FlexSim 18.1.1
task sequences
· 4
5 |100000

Up to 12 attachments (including images) can be used with a maximum of 23.8 MiB each and 47.7 MiB total.

1 Answer

Joshua S avatar image
0 Likes"
Joshua S answered yoni A commented

Is this flow kind of what you are looking for?12164-load-unload-task-sequence-change.fsm