Hi,

How to go to the parking station recharging when AGV is idle,and stop to recharge and go to work when AGV receives new works

FlexSim 18.2.3
agv recharge
· 1
5 |100000

Up to 12 attachments (including images) can be used with a maximum of 23.8 MiB each and 47.7 MiB total.

gilbert jerald avatar image gilbert jerald commented ·

@liu Y4

Hi,

Based on your question I have attached a sample model where AGV will use both parking and recharging station whenever need. this model will give you some basic information for you to work in AGV models. Have a look at it

support-agv-tutorial-battery.fsm

Thanks

0 Likes 0 ·

1 Answer

David Seo avatar image
2 Likes"
David Seo answered Isaac Litster rolled back

@liu Y4

You can find it to solve your issue about recharging and moving parking lot in Process Flow > Add Task Executer PF > AGV menu option.

You can find the detail Process Flow activities block about recharging and moving it when below battery level.