Hi,
I am trying to control the conveyor capacity using "Close and Open Ports" triggers on the upstream queue. I am able to control the maximum content of conveyor but after a downtime event, flow items do not pass through conveyor.ControlledConveyorCapacity.fsm

FlexSim 22.2.0
conveyorglobal varmtbfmttr
5 |100000

Up to 12 attachments (including images) can be used with a maximum of 23.8 MiB each and 47.7 MiB total.

1 Answer

·
Jason Lightfoot avatar image
1 Like"
Jason Lightfoot answered Jason Lightfoot commented

Here's a better approach where the conveyor controls the entryTransfer's input port based on the maxContent label.

controlledconveyorcapacity_jl.fsm

Another way would be to change the spacing to ensure the capacity is enforced.


· 2
5 |100000

Up to 12 attachments (including images) can be used with a maximum of 23.8 MiB each and 47.7 MiB total.

Rahul T5 avatar image Rahul T5 commented ·

Thanks for the input Jason,
Not sure which label types to add for "inTransfer" and "maxContent". Can you advise?

1666054500070.png

0 Likes 0 ·
1666054500070.png (12.3 KiB)
Jason Lightfoot avatar image Jason Lightfoot ♦ Rahul T5 commented ·
The maxContent is just an numeric, but inTransfer is a pointer label which you then set by using the sampler (pipette icon).