Hello, Flexsim Gurus!

I have simulated a manufacturing site that operates 8 hours/day. I want to determine the total production if the site was operated for a period of 5 days. How can I achieve this using the experimenter tool?

I will appreciate a detailed response as it is my first time using this tool.


FlexSim 23.2.0
experimenterperformance measuresexperimenter statistics
· 2
5 |100000

Up to 12 attachments (including images) can be used with a maximum of 23.8 MiB each and 47.7 MiB total.

Joerg Vogel avatar image Joerg Vogel commented ·

@MC Bunji, please go with this tutorial https://docs.flexsim.com/en/23.2/Tutorials/AdditionalTools/Tutorial4Experimenter/4-1ExperimentJob/4-1ExperimentJob.html

If you have still a question, then be precise what you want and what is not working as intended.

0 Likes 0 ·
Natalie White avatar image Natalie White commented ·

Hi @MC Bunji, was Jason Lightfoot's answer helpful? If so, please click the "Accept" button at the bottom of their answer. Or if you still have questions, add a comment and we'll continue the conversation.

If we haven't heard back from you within 3 business days we'll auto-accept an answer, but you can always comment back to reopen your question.

0 Likes 0 ·

1 Answer

Jason Lightfoot avatar image
1 Like"
Jason Lightfoot answered Jason Lightfoot edited

Does your model stop during the non-working time? If not run for 40 hours or add timetables.

If it does then just set your experiment length to 5 days.

5 |100000