How to use AGV controlpoint simulate the working station?

1.fsmWhen AGV LOAD item, and travel to final destination. When AGV through the agv control point before final destination. How i let agv stop at the control point which stand for working station for process time?

1692240781841.png

FlexSim 22.0.16
agv
1692240781841.png (387.4 KiB)
1.fsm (107.5 KiB)
5 |100000

Up to 12 attachments (including images) can be used with a maximum of 23.8 MiB each and 47.7 MiB total.

Jason Lightfoot avatar image
0 Likes"
Jason Lightfoot answered Zhun Z commented

You can use an object process flow to issue a preempting tasksequence to travel to the control point and delay onPreArrival.

AGVcontrolPointsAsStations.fsm


· 1
5 |100000

Up to 12 attachments (including images) can be used with a maximum of 23.8 MiB each and 47.7 MiB total.

Zhun Z avatar image Zhun Z commented ·
Thanks, this is a perfect solution!
0 Likes 0 ·
Felix Möhlmann avatar image
0 Likes"
Felix Möhlmann answered Zhun Z commented

You can define waypoint logic that gets executed when an AGV arrives at specified control points in the AGV network properties.

1692252474088.png

1-fm.fsm


1692252474088.png (20.1 KiB)
1-fm.fsm (201.1 KiB)
· 1
5 |100000

Up to 12 attachments (including images) can be used with a maximum of 23.8 MiB each and 47.7 MiB total.

Zhun Z avatar image Zhun Z commented ·
Thank you!
0 Likes 0 ·

Write an Answer

Hint: Notify or tag a user in this post by typing @username.

Up to 12 attachments (including images) can be used with a maximum of 23.8 MiB each and 47.7 MiB total.