Event when slug is built?

Is there a way to have a Wait for Event activity in process flow wait for a slug to be built on a conveyor? I was thinking of using Conveyor.SlugBuilder.state == 2 // Ready - the slug has achieved its ready criteria, but I can't see how to enter that criteria into the Wait for Event activity.

FlexSim 23.1.1
wait for eventslug building
· 1
5 |100000

Up to 12 attachments (including images) can be used with a maximum of 23.8 MiB each and 47.7 MiB total.

Jeanette F avatar image Jeanette F ♦♦ commented ·

Hi @craig-dickson, was Felix Möhlmann's answer helpful? If so, please click the "Accept" button at the bottom of their answer. Or if you still have questions, add a comment and we'll continue the conversation.

If we haven't heard back from you within 3 business days we'll auto-accept an answer, but you can always comment back to reopen your question.

0 Likes 0 ·

1 Answer

Felix Möhlmann avatar image
0 Likes"
Felix Möhlmann answered

The Merge Controller object has events pertaining to slug building. You'd connect it to the relevant conveyor(s), set it to do nothing itself and use the events to trigger the slug release.

capture.png

You can look at the Gap-Optimizing Merge Controller Process Flow for an example.