Hello, I have a subflow and it shows no objects attached. I cannot find where my disconnect is. I wonder if the token is stuck in Create TS for this reason? Primer_4-3c.fsm
Hello, I have a subflow and it shows no objects attached. I cannot find where my disconnect is. I wonder if the token is stuck in Create TS for this reason? Primer_4-3c.fsm
Hi @Stella ,
It will say "No Objects attached" like that until the first token is sent to the subflow, which happens at time 6.43 seconds.
The tokens are held up at Create TS because there are other tasks sequences ahead of them in the task sequence queue of the dispatcher.
By time 41 the first token adds its first task to that task sequence.
Then around time 113 the operator gets stuck because the task sequence created by the sub flow doesn't have a Finish Tasksequence activity.
So onlky thing I tihnik you need to change is adding that "Finish Tasksequence" activity.
11 People are following this question.
FlexSim can help you understand and improve any system or process. Transform your existing data into accurate predictions.
FlexSim is a fully 3D simulation software environment. FlexSim can be used to simulate any process in any industry.
FlexSim®, FlexSim Healthcare™, Problem Solved.®, the FlexSim logo, the FlexSim X-mark, and the FlexSim Healthcare logo with stylized Caduceus mark are trademarks of FlexSim Software Products, Inc. All rights reserved.
Privacy | Do not sell or share my personal information | Cookie preferences | Report noncompliance | Terms of use | Legal | © Autodesk Inc. All rights reserved