I have one issue with my AGV problem

prueba-dos-agv-2º-prueba.fsmHi forum i have one question. In my model there are two AGV (TaskSequence1 and TaskSequence2) My question is why can i use use this two AGV separately. For example whe processor1 end the process the TaskSequence1 make the work. When the processor2 end the process the TaskSequence2 make the work

Thanks for all

Choose One
agvquestion
· 8
5 |100000

Up to 12 attachments (including images) can be used with a maximum of 23.8 MiB each and 47.7 MiB total.

1 Answer

Michael Kramer avatar image
0 Likes"
Michael Kramer answered

Use the built-in AGV process flow to handle work balancing 13815-prueba-dos-agv-2º-prueba-1.fsm. If there's not enough work, AGVs will park. If there's work, they will do it, as long as the control points are connected using "NextLookforWork."

The attached model is set up with the AGV process flow but it will deadlock because the layout needs to change. Check out the directions in the AGV process flow window and it will help you.