question

liu Y4 avatar image
0 Likes"
liu Y4 asked tannerp commented

AGV recharge question

Hi,

How to go to the parking station recharging when AGV is idle,and stop to recharge and go to work when AGV receives new works

FlexSim 18.2.3
agv recharge
· 1
5 |100000

Up to 12 attachments (including images) can be used with a maximum of 23.8 MiB each and 47.7 MiB total.

gilbert jerald avatar image gilbert jerald commented ·

@liu Y4

Hi,

Based on your question I have attached a sample model where AGV will use both parking and recharging station whenever need. this model will give you some basic information for you to work in AGV models. Have a look at it

support-agv-tutorial-battery.fsm

Thanks

0 Likes 0 ·

1 Answer

·
David Seo avatar image
2 Likes"
David Seo answered Isaac Litster rolled back

@liu Y4

You can find it to solve your issue about recharging and moving parking lot in Process Flow > Add Task Executer PF > AGV menu option.

You can find the detail Process Flow activities block about recharging and moving it when below battery level.

5 |100000

Up to 12 attachments (including images) can be used with a maximum of 23.8 MiB each and 47.7 MiB total.

Write an Answer

Hint: Notify or tag a user in this post by typing @username.

Up to 12 attachments (including images) can be used with a maximum of 23.8 MiB each and 47.7 MiB total.