Hi Guys,
In my model as attached, i have set the schedule down time for sorter, every time when sorter is down, i need to conveyor to stop and the item stay on the conveyor, conveyor to be resumed when sorter is up, anyone can help?
Best regards
Hi Guys,
In my model as attached, i have set the schedule down time for sorter, every time when sorter is down, i need to conveyor to stop and the item stay on the conveyor, conveyor to be resumed when sorter is up, anyone can help?
Best regards
Hi @Boey TS,
I think the best way to do this is to use an event triggered source in process flow then set the conveyor speed.
First, make the following process flow:
conveyorsetspeed(model().find("Conveyor1"), 0);
Repeat the 2 steps for Sorce: Sorter Resume, but instead select "Sorter1: On Resume" and set the speed to whatever you would like.
I hope this helps!
12 People are following this question.
FlexSim can help you understand and improve any system or process. Transform your existing data into accurate predictions.
FlexSim is a fully 3D simulation software environment. FlexSim can be used to simulate any process in any industry.
FlexSim®, FlexSim Healthcare™, Problem Solved.®, the FlexSim logo, the FlexSim X-mark, and the FlexSim Healthcare logo with stylized Caduceus mark are trademarks of FlexSim Software Products, Inc. All rights reserved.
Privacy | Do not sell or share my personal information | Cookie preferences | Report noncompliance | Terms of use | Legal | © Autodesk Inc. All rights reserved