I have a model built using the 3D Flow approach. Let's say it consists of a number of processors and also a number of combiners that use the output of the processors to create a final assembly. However, the production requirements for the components and products from each of these changes from day to day for the next 30 days after which the simulation must end.
Each day consists of two shifts of 6 hours each. I know I can use the timetable option to create each shift. I also know that I can feed the production data to the processors and combiners using the Read from Excel option. But how I can I ensure that the production parameters for the machines change every 2 shifts (1 day) according to the 30-day production plan? I want to simulate this using the 3D approach.
Any help regarding this is much appreciated!