question

Stan Davis avatar image
0 Likes"
Stan Davis asked Eric M commented

Release Resource Destroys Assign To Label Vice NULL Value

Why is the label created via the 'Acquire Resource - Assign To Label' subsequently destroyed after being used in the 'Release Resource - Resource Assigned To' instead of just having a NULL value afterward?? This seems counter to other labels that can have NULL values. Thanks

FlexSim 21.1.5
processflowflexsim 21.1.5
5 |100000

Up to 12 attachments (including images) can be used with a maximum of 23.8 MiB each and 47.7 MiB total.

1 Answer

·
Eric M avatar image
0 Likes"
Eric M answered Eric M commented

Hi @Stan Davis, I think this is mostly to avoid potential cluttering of the labels since there's generally no more need for the label once the resource has been released. For example, if a token acquired 5 resources at different times and they each were assigned to a different label name, by the end the token would have 5 empty labels. Is there a particular reason you're hoping to keep the empty label?

· 2
5 |100000

Up to 12 attachments (including images) can be used with a maximum of 23.8 MiB each and 47.7 MiB total.

Stan Davis avatar image Stan Davis commented ·
Understood. I just thought it was a little inconsistent. Also, if I need to retain the last acquired resource value for some reason, I can just copy it to a 'regular' label after being acquired. Thanks.
0 Likes 0 ·
Eric M avatar image Eric M Stan Davis commented ·

That's a fair point. There's actually a built in option in the release activity to let you store the released resource on a new label.

1628876492504.png

0 Likes 0 ·
1628876492504.png (12.5 KiB)

Write an Answer

Hint: Notify or tag a user in this post by typing @username.

Up to 12 attachments (including images) can be used with a maximum of 23.8 MiB each and 47.7 MiB total.