Hello, every time you help me a lot.
There is an issue related to AGV operation.
1. Load 2 boxes from Queue
2. AGVs go to Processors.
3. Unloading(ULD) the product for which work has been completed in the Processor.
4. Loading(LD) the product on the AGV that has not been worked on.
(AGV has 3 buffer)
5. go to another Processor and repeat (3-4)
*so AGV has 2 box which work has been completed
using Process Flow, or Or is it possible to solve the issue by utilizing the "break to" property of TaskExecuter?
Please note that we cannot upload flexsim files or images due to security concerns. :(
I would appreciate it if you let me know by text, or if the best way is to create an example file.
Thank you.