question

Sharan Nitin avatar image
0 Likes"
Sharan Nitin asked Arun Kr edited

How to Push a node into the List (Process Flow)?

FlexSim 18.1.0
push to listnodehow to control push pull items according to the entries of listpush to list based on label
5 |100000

Up to 12 attachments (including images) can be used with a maximum of 23.8 MiB each and 47.7 MiB total.

1 Answer

·
Arun Kr avatar image
2 Likes"
Arun Kr answered Arun Kr edited

Hi Sharan Nitin,

While using process flow, when you want to push a node to a list. You need to use a push to list activity and the push value must be the reference to the node, which you want to push.

The term node is a generic term in FlexSim. A node can be an Object node, numeric data node, string data node or a pointer node. Also, I am attaching a sample model for your reference.support-nithin.fsm

Regards,

Arun KR


support-nithin.fsm (19.0 KiB)
5 |100000

Up to 12 attachments (including images) can be used with a maximum of 23.8 MiB each and 47.7 MiB total.

Write an Answer

Hint: Notify or tag a user in this post by typing @username.

Up to 12 attachments (including images) can be used with a maximum of 23.8 MiB each and 47.7 MiB total.