Hello , I have a question is that I do not know how to make a group of operators in process flow to follow a sequence .
Hello , I have a question is that I do not know how to make a group of operators in process flow to follow a sequence .
Hi @eduardo.s8, was joerg.vogel's answer helpful? If so, please click the red "Accept" button on their answer. Or if you still have questions, add a comment and we'll continue the conversation.
A group is not a valid reference as a direct reference for tasks. A member of a group is valid. You can give a resource activity a group for reference. But you will acquire only one operator for a task. Typically you build a subflow structure or an instanced process flow wherein you acquire and insert tasks for each operator. Thus you have the same structure for all operators of a group built only once.
15 People are following this question.
FlexSim can help you understand and improve any system or process. Transform your existing data into accurate predictions.
FlexSim is a fully 3D simulation software environment. FlexSim can be used to simulate any process in any industry.
FlexSim®, FlexSim Healthcare™, Problem Solved.®, the FlexSim logo, the FlexSim X-mark, and the FlexSim Healthcare logo with stylized Caduceus mark are trademarks of FlexSim Software Products, Inc. All rights reserved.
Privacy | Do not sell or share my personal information | Cookie preferences | Report noncompliance | Terms of use | Legal | © Autodesk Inc. All rights reserved