Use the Unload activity to make a task executer (such as an Operator or Transporter) unload an object in the 3D simulation model. For example, you can make a task executer drop off a flowitem at a processor or queue.

The Unload activity creates an unload task sequence and dispatches it to a task executer. Optionally, the task may be appended onto an already existing task sequence. See Create Task Sequence activity for more information. Also see Task Sequences for more general information about task sequences.

Connectors

The Unload activity only allows one connector out. See Adding and Connecting Activities for more information.

Properties

The following image shows properties for the Unload activity:

Each of these properties will be explained in the following sections.

  • Name You can change the name of the activity using the Name box. See Name for more information about this property.
  • Font The Font button opens a window to edit the activity's background color and font properties. See Font for more information about this property.
  • Statistics The Statistics button opens the activity's statistics window. See Statistics for more information about this property.
  • Executer / Task Sequence Use the Executer / Task Sequence box to determine which task executer or task sequence should receive the task. See Executer / Task Sequence for more information about this property.
  • Item Use the Item box to determine which item or object should be unloaded. Typically this is a flowitem, however, other objects can be used. There are many different ways to reference flowitems and objects in the model. Below are just a couple of examples:
    • You can use a Create Object activity to create a flowitem in the 3D model and assign the appropriate label to that object.
    • You can create a Wait For Event or Event Triggered Source activity that listens for flowitems arriving at a fixed resource and assigns a label to those entering flowitems.
  • StationUse the Station box to select the object from which the task executer should unload the item to. Usually you will point to a fixed resource (such as a processor or queue) but you can also point it to another task executer.
  • Wait Until CompleteIf the Wait Until Complete box is checked, the token will be held in the activity until this task has been completed.
flexsim users manualuser manuals
5 |100000

Up to 12 attachments (including images) can be used with a maximum of 23.8 MiB each and 47.7 MiB total.

Article

Contributors

paul.t contributed to this article

Navigation

FlexSim 2016.1