Delay (Task Sequence)   

Use the Delay (task sequence) activity to make a task executer (such as an Operator or Transporter) delay for a specific period of time in the 3D simulation model. For example, a delay could represent a task that takes a specific amount of time to complete such as cleaning a machine, assembling a product, etc.

The Delay activity creates a delay task sequence and dispatches it to a task executer. Optionally, the task may be appended onto an already existing task sequence. See Create Task Sequence activity for more information. Also see Task Sequences for more general information about task sequences.

Make Sure You're Using the Correct Delay Activity
Don't confuse the Delay (task sequence) activity with the the general Delay activity .

Connectors

The Delay activity only allows one connector out. See Adding and Connecting Activities for more information.

Properties

The following image shows properties for the Delay activity:

Each of these properties will be explained in the following sections.

  • Name You can change the name of the activity using the Name box. See Name for more information about this property.
  • Font The Font button opens a window to edit the activity's background color and font properties. See Font for more information about this property.
  • Statistics The Statistics button opens the activity's statistics window. See Statistics for more information about this property.
  • Executer / Task Sequence Use the Executer / Task Sequence box to determine which task executer or task sequence should receive the task. See Executer / Task Sequence for more information about this property.
  • Delay TimeThe Delay Time defines the amount of time that the task executer will be delayed.
  • State Use the State box to determine which state the task executer will be in during the delay task (such as idle, busy, on break, etc.). The task executer's state is useful if you want to record statistics about how long the task executer is in a particular state. Click the arrow next to the State box to see a menu of available states. You can also specify user defined states.
  • Wait Until CompleteIf the Wait Until Complete box is checked, the token will be held in the activity until this task has been completed.
flexsim users manualuser manuals
5 |100000

Up to 12 attachments (including images) can be used with a maximum of 23.8 MiB each and 47.7 MiB total.

Article

Contributors

paul.t contributed to this article

Navigation

FlexSim 2016.1